More than half of the restaurants that received permits through New York City’s permanent outdoor-dining program waited longer than 19 months, according to an investigation released by City Comptroller Mark Levine. The finding covers applications processed since Dining Out NYC launched in March 2024 and contrasts with the Department of Transportation’s communicated timeline of up to eight months. The report argues that delays have cost restaurants usable seating and made it harder for owners to plan staffing, construction and seasonal service.

The comptroller’s review examined Department of Transportation data through June 15, 2026. Of 4,911 applications submitted by that date, 1,405 had produced licenses, or 28.6 percent. Another 2,115 applications were pending with the agency, while other applications had been denied or cancelled. The figures describe a snapshot of the backlog, not the current total, because the department accelerated submissions later in the year and more permits have since moved to the comptroller for registration.

Processing improved substantially after the investigation began. From the program’s launch through January 2026, the Transportation Department sent an average of 29 permits per month to the comptroller. Beginning in February, that average rose above 228, and July reached 475 submissions. The report credits that progress but says it does not erase earlier waits or establish that new applicants will consistently receive decisions within a predictable period.

The investigation identifies data management as a central weakness. According to the comptroller, the Transportation Department could not show how long applications spend at each internal and external review stage or provide a complete system for tracking why permits are denied. Without milestone dates and consistent categories, managers cannot easily distinguish time spent waiting for agency review from time spent with community boards, the City Council or applicants correcting plans.

Restaurant owners also face technical requirements that can be difficult to prepare without professional help. Application packages may require detailed drawings and site-clearance information, even though some of the underlying information is already available through city data systems. The comptroller recommends tools that could prefill location details, help owners sketch furniture layouts and identify applications that have few site-specific barriers and may qualify for faster processing.

The permit structure requires both a Transportation Department license and a revocable-consent agreement for the use of public space. It can involve community-board review, public notices, city contracts systems, the Council and comptroller registration. The comptroller says its office registers submissions in an average of 7.9 days and has authorized eligible restaurants to begin operating once the department files a permit for registration. Most of the delay described in the report occurs before that point.

Outdoor dining has become economically important for restaurants, but participation has fallen sharply from the emergency pandemic-era program. The comptroller’s office says just under 2,500 of the city’s roughly 27,000 restaurants now participate, compared with nearly 13,000 at the peak. A new city law allows roadway cafes to operate year-round, reducing the cost of seasonal dismantling and storage, but those benefits depend on restaurants receiving a permit in time to use the space.

The report recommends performance targets for every stage, routine public reporting and a plan to clear the remaining backlog. It also notes a November ballot proposal that could shorten some external reviews, while emphasizing that administrative improvements are possible regardless of the vote. For restaurant owners, the immediate issue is predictability: a process can include safety and public-space safeguards without leaving businesses unable to tell when an application will reach a decision.

Sources: NYC Comptroller’s Office; NYC Comptroller investigation report. Reviewed October 29, 2026. Development: October 27, 2026.